Reschedule Tasks

Reschedule allows for planning template tasks to be moved from one workpack to another.

To reschedule tasks, proceed as follows:

  1. On the PLANNING or WORKPACKS screen, on the Tasks tab, select the relevant tasks (you can use multi-select) and choose Reschedule from the toolbar.

  2. In the Select Workpack dialog, select the workpack to which you want to reassign the planning template task.

  3. Click OK to move the task to the selected workpack.

  4. On the PLANNING screen, go to the Planning Templates tab and select the planning template that has been changed due to rescheduling.

  5. Choose Update in the toolbar to update the planning template.

Note

You can only reschedule tasks that are associated with a planning template. The reschedule option is not available for tasks that have been imported or manually created.