Add/Edit Planning Task Dialog
The Add Planning Task and Edit Planning Task dialogs allow you to define the properties of a planning task and manage its related data.
See below for the description of fields in the Add Planning Task/Edit Planning Task dialogs.
Field/Checkbox Name |
Description |
|---|---|
Planning Template |
Specifies the planning template that contains this planning task. |
Asset |
Specifies the asset on which the task is to be performed. Select an asset from the hierarchy. You must specify either an asset or an asset type. |
Asset Type |
Use this option if the task applies to a group of assets of a specific type rather than to a single asset. Click the ellipsis button to select an asset type. |
Ad Hoc Task |
If selected, tasks generated from this planning task are flagged as ad hoc tasks. |
Start KP/EL / End KP/EL |
Defines the start and end kilometre point (KP) or elevation location where the task is to be performed. These fields are optional. |
Event Type |
Specifies the type of event to be scheduled. The event type identifies the inspection method to be scheduled and carried out. This field is mandatory. |
Schedule Type |
Optional field used for grouping or categorising planning tasks. |
Category |
Optional task category used to further group tasks (for example, tasks that require rope access, tasks that should only be undertaken on days ending in a ‘y’, etc.). |
Reference Number |
Company-specific reference number for the planning task. When the planning template is applied and a task is created, this reference number is inherited by the task. |
Requires Shutdown (Manual) |
Indicates whether the asset requires shutdown before the task can be completed. |
Requires Shutdown (Lookup) |
Select a Yes / No AIG field that provides the shutdown requirement for this task. |
Approx Timing (Manual) |
Estimated time required to complete the task. This value is used to estimate the overall duration and, optionally, the cost of workpacks. |
Approx Timing (Lookup) |
Select a Numeric AIG field that contains the estimated time to complete this task. |
Order Number |
Specifies the order in which tasks are intended to be completed (for information purposes only). For example, if an asset must be cleaned before GVI, assign the Cleaning task a lower order number than the GVI task. Repeated values are allowed. The Order Number also determines the order in which tasks appear in the inspector’s list in IC-Inspector (see Tasks Screen). |
Instructions (Manual) |
Enter task-specific instructions. These instructions can be included in workpack reports to guide inspection engineers. |
Instructions (Lookup) |
Select the AIG field that contains instructions for this task. |
Start (Manual) |
Specifies the first occurrence (or workpack) at which the task is created. This can be a numeric value representing the first occurrence, or a date value (such as “last inspected date”). If a date value is used, the Update/Apply process calculates the corresponding occurrence based on that date. |
Repeat (Manual) |
Enter a value that defines the frequency that the task is to be created. This can be either a numeric value (which will be considered a frequency), or a date value (such as “next inspection date”). For example, if you enter 3 in this field, a task will be created at every third occurrence. If a date is used, the Update/Apply process will calculate the occurrence based on the date. |
Start (Lookup) |
Choose the AIG field that defines the first occurrence (or workpack) to create this task. This can either be a numeric value that specifies the first occurrence, or a date value (such as “last inspected date”). If a date-type field is used, it automatically populates the Due Date field for planning tasks generated by this template. |
Repeat (Lookup) |
Select the AIG field that defines how often the task is created. This can be a numeric field representing a frequency or a date-type field (such as “next inspection date”). The Update/Apply process calculates the occurrence based on the date. |
Create Action |
Determines when exactly a task is created. Choose from the following options:
|
Anomaly Action |
If this planning task is related to a specific anomaly action, click the ellipsis button and choose the relevant anomaly action from the list. |
Details |
Reference or source information for the planning task, for example a risk-based assessment or a company procedure number. |
See Checking History.