Complete Tasks
In IC-Inspector, you can complete tasks in one of the following ways:
By swiping the task’s row on the Tasks screen (see Tasks) and tapping on Mark as Complete:
By changing the status of the task on the Event Details screen (see Maintain Event Details).
To set the status to completed, tap Status on the top of the screen and select Mark as Complete. You can get to the Event Details screen either by tapping on a task from the list of tasks on the Tasks screen, or by tapping on a task from a drawing (see Check Tasks in a Drawing).
When you complete a task, it will be marked as completed. When the task has been completed, it will be uploaded to the server during the next synchronisation (see Synchronise).