Assign Risk Models
You can assign risk models to individual assets from the ASSETS, PLANNING or WORKPACKS screen as described below.
Note
The same risk model can be assigned to an asset multiple times. Each assignment creates a separate risk assessment that can be managed independently.
Prerequisites
Before assigning a risk model, ensure that:
Risk charts and risk models have been configured (see Configure Risk Charts and Configure Risk Models).
The risk model has been assigned to the asset type of the asset (see Assign Risk Models to Asset Type).
Assign a Risk Model to an Asset
Select the asset in the asset tree and open the Risk tab.
Click
Assign to <name of asset> in the toolbar.Select the required risk model.
Note
Only risk models that have been assigned to the asset’s type are available for selection.
Click OK.
Copy Risk Models to Multiple Assets
You can assign risk models to multiple assets at a time by copying existing risk assessments from an asset.
Select the asset whose risk assessment you want to copy and open the Risk tab.
Select the required risk assessment and choose one of the following options from the toolbar:
to copy the risk assessment without its scenarios
to copy the risk assessment together with the scenarios beneath it.
Note
You can select only a single risk assessment at a time.
In the dialog that opens, select the target assets. If required, you can switch to a different asset view.
Click OK.
Result
The selected risk assessments are copied to the target assets together with the values assigned to factors and categories in the risk model. If you selected Risk Assessment and Scenarios, the associated scenarios are copied as well.